Digital positioning speeds up hospital build

By Leila Steed19 January 2021

Engineering specialist Züblin completes piling works at Austrian hospital four weeks early with Leibherr’s LIPOS position system

Züblin Spezialtiefbau used a Liebherr LB28 drilling rig equipped with the equipment manufacturer’s LIPOS positioning system to install over 1,000 concrete piles for the new hospital building in Oberwart, Austria.

Groundworks engineering specialist Züblin Spezialtiefbau has used a Liebherr LB28 drilling rig equipped with the equipment manufacturer’s LIPOS positioning system for the first time, to complete piling works to a new hospital in Oberwart, Austria.

The Germany-based company, which has been operating across Europe for over 100 years, installed a total of 1,310 piles for the Burgenland Hospital Association’s (KRAGE’s) new 23,000m² medical building. Upon completion it will provide medical, nursing and therapeutic care to the region. 

Use of the LIPOS technology enabled the extensive piling works, which were carred out to avoid subsequent settlement and damage to the new hospital, to be completed in three months – four weeks ahead of schedule.

The works saw Züblin take accurate measurements of the jobsite and the required position of each pile and transferred the data as a digital drilling map to the LIPOS positioning system.

The company then installed the piles, which measured 630mm in diameter, using a Liebherr THS110 concrete pump. Züblin placed the piles at a maximum depth of 16m using the continuous flight auger (CFA) method.

A Züblin worker measures the jobsite to create a digital drilling map for the piles. Züblin measured the jobsite to create a digital drilling map.

Harald Fugger, Züblin Spezialtiefbau’s site manager, “The LIPOS positioning system is ideally suited for completing jobsites, especially using the CFA method. It has proven itself well on the jobsite and makes working processes easier allowing continuous real time control and monitoring. Quality management is considerably improved through the automatic recording of the processes. The LIPOS system is basically self-explanatory for the operator and convinces through easy handling.”

Liebherr's LIPOS positioning system monitor According to Liebherr, without the LIPOS position system drilling points would have to be newly measured, drawn and marked at least three times a day.

Liebherr’s LIPOS positioning system enables the operator to see the drill’s location on a monitor in the cabin. According to the manufacturer, using the positioning systems means operators have centimetre precision all the time.

The manufacturer said, “The operator no longer has to watch out for ground marking or the concrete hose. He can concentrate on important things, is more flexible and independent, and therefore, quicker in handling the drilling rig.”

NEWSLETTER
Delivered directly to your inbox, Construction Technology Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Andy Brown Editor, Construction Technology Tel: +44 (0)1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0)1892 786223 E-mail: simon.kelly@khl.com
Latest News
Hexagon offers digital twins of entire cities
Munich, Milan, Amsterdam, Stockholm, Tokyo and New York among cities that are available as digital twins
Hexagon to host live tech summit
Live technology summit to showcase Hexagon’s new autonomous solutions
Peri launches digital concrete monitoring kit
Temperature Monitoring and Concrete Maturity Kit takes temperature readings from different points in concrete